Assumptions
Assume all time estimates throughout the case are accurate.
Assume whole days are needed to complete an activity (i.e., even if an activity
takes only a few hours, for planning purposes assume it takes a full day).
Assume that on any given day, if needed, any number of different activities can be performed simultaneously.
Assume seven-day weeks (i.e., weekdays, Saturdays and Sundays are all avail- able for performing any project activities and count towards any required lead-times).
Question: When is the soonest the wedding can take place, assuming nothing is expedited (except for the 90-day rush ordered dress)? Instead of providing a date as an answer you may want to indicate in how many days can the wedding take place. Can Meg and Adam make the July date? If not, which activities (if any) should Meg expedite to have the wedding on the July date and why? Which additional activities (if any) should Meg expedite in order to have the wedding on the June date?