Devry PROJ586 Week 8 Final Exam Latest 2015 November 2. Question : (TCO H) The fundamental purpose of the post-project evaluation is to improve future projects. An important component of this evaluation is The project audit The closure checklist Lessons learned Customer satisfaction report Question 7. Question : (TCO A) The project plan is executed in the _____. initiating phase planning phase executing phase closing phase Question 11. Question : (TCO C) Calculate the earliest finish for Task B if its predecessor Task A finishes on Day 3 and the duration of Task B is 2 days. Day 5 Day 3 Day 1 This cannot be calculated based upon the information given. Question 12. Question : (TCO H) A project audit provides an opportunity to evaluate issues and concerns to determine potential improvements. Some benefits of a project audit are: Reduce project risk time and cost overruns Keep the scope of the project under control Allow the project team to have good performance Recommend outsourcing on other projects