Include the following information/deliverables.
Background/summary
HVAC & Duct System:
Layout (line drawings)
Show all duct sizes and cfms use round ductwork
Show diffuser locations and type (use a schedule Titus Brand)
Show terminal units (VAV, FCU, etc.) (use a schedule Trane Brand)
Show primary HVAC units on layout (use schedule Trane Brand)
Hand in one cut sheet per unit type (diffusers, terminal units, boiler, AHU, etc.)
For the schedule(s) of all unit types, include data such as cfm, gpm, Btu/hr heating, Btu/hr cooling, pressure loss, and any other relevant data.
Piping System:
On a separate sheet, show piping layout include gpm and pipe size
Show any equipment the piping is connected to
Load Layout Diagram: For each zone, on a separate sheet, include the following:
Show terminal units and branch ductwork/diffusers
For each zone, list your calculated design heating and cooling loads and fresh air
– you may integrate a schedule with this diagram
Controls:
List how you will control temperatures in the zones
List if/how you will control air and hydronic variations of flow and temperature
Equipment shut off / turn on control and schedule
Energy & Cost Calculations:
List how much energy you expect your HVAC system to use per year.
List how much energy cost you expect your HVAC system to use per year.
List how much energy (MMBtu/yr) you expect your HVAC system to use per year.
List how much energy (MMBtu/sqft) you expect your HVAC system to use per square foot.
Also include:
All calculations, sample calc, info, spreadsheets, assumptions, references
Format:
Coversheet
Table of Contents
System Overview: What system you selected and why you selected it
System Specifications: Diagrams, schedules, controls logic, cut sheets, etc.
Appendices:
Abstract/Overview of Project
Design considerations, heating/cooling loads, fresh air calc., etc.
Sample Calcs.
Spreadsheets
Assumptions
Additional Info as needed
Grading Ruberic:
Select your systems based on:
10% Comfort and aesthetics
20% Energy use (MMBtu/sqft)
20% Energy cost/yr
10% Accuracy of selection/sizing
40% – Deliverables
Givens:
Average occupancy: 4-8 people; sometimes training sessions will be held with more people (1/mth for 1-2 hours, typically 15-20 people).
1 toilet (water closet) and 1 urinal in the Restroom.
Mechanical Room has domestic water & hot water heater; electrical; and HVAC system.
Desks/cubicles in corner
Electricity ($0.11/kWh)
Natural Gas ($0.70/therm)