see the attached file a) Draw the Network Chart – include task id, duration, ES, EF, LS, LF, slack b) What is the critical path? What is slack time for tasks F and G? c) Would the management of


see the attached file 

a)  Draw the Network Chart – include task id, duration, ES, EF, LS, LF, slack

b)  What is the critical path? What is slack time for tasks F and G?

c)  Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not?

d)   Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not?

e)  What is slack time and lag time?

f)  Can the critical path of a project change? Why or why not?