Developing a Closure Plan
This week, you’ll create the closure plan. The project turned out to be successful with a few minor issues that must be addressed in the Project Post-Implementation Evaluation Report under Lessons Learned. The issues were as follows:
- Not all 100 computers were licensed to run the new software
- The staff were resistant to the change and did not want to attend training
- The IT department could not remove the old computers because there was no place to store them
Analyze the critical success factors, and state their conclusion and the lessons learned.
Submission Details:
- Create the report in 800-words in a Microsoft Word document; save it as W5_A2_LastName_FirstInitial.docx.
- Submit the document to the Submissions Area by the due dateassigned.