Part 1
- Read Whistler Ski Resort Project on pages 202-203.
- Create a table (using Table 6.1 on page 175 as your guide) that lists the activity,
description, and preceding activities (required before the activity can start) for this
project. - Using the Figure 6.4 on page 76 as a guide, create an activity-on-node (AON) project
network for the project. - After you complete your network, use a different color arrow/line to identify the
critical path.
Note You do not need to identify forward and backward passes or identified slack time for this assignment; simply create a completed network of activities like Figure 6.4.
Part 2
Briefly (250 words minimum) describe your choice of the critical path. Why are the non- critical activities not on the path? What impact would eliminating these activities from the plan have on the overall project?